Epic Planning and Sustainability Management

Epic Planning

The Lifecycle of an Epic

  1. Most epics start with a discovery based on a client requirement. (For internal projects, the client is OpenCraft).
  2. An epic is created based on the corresponding discovery and starts in the Prospect column.
  3. The discovery and corresponding estimates are shared with the client, and the epic is moved to Offer / Waiting on client.
  4. If the client accepts the work, the epic is moved to Accepted.
  5. Once actual development starts, the epic is moved to In Development.
  6. Once the client's requirements are met, and the client has access to the completed work, the epic can be moved to Delivered to client / QA.
  7. The epic should be moved back from Delivered to client / QA to In Development if the client requests additional work or modifications that need development.
  8. When all the work in the epic is complete (for instance if all upstream PRs have been reviewed and merged) the epic can be moved to Done.

Recurring epics are generally not based on a project or discovery, but are used to track work for different cell roles (or long-running maintenance contracts for specific clients).

Tracking Epic Status

  • Each cell has its own Epics board and epics, and is responsible for making sure that the projects represented by the epics are being properly delivered based on the lifecycle described above.
  • To find the epics board for your cell, go to Boards > View all boards > Epics - <your cell> in JIRA. (Note that if you've recently accessed the board, it may also be listed under Boards > Recent boards.)
  • Every sprint, status changes of individual epics from the past sprint should be reviewed and evaluated to be able to keep both the Epics board and the epic planning spreadsheet up-to-date. This involves making sure that:
    • Each epic that is In Development has an epic update.
    • New epics are moved through the set of initial states (Prospect, Offer / Waiting on client, Accepted) as appropriate until they reach In Development.
    • Epics that have become blocked on the client are moved to Offer / Waiting on client.
    • Delivered epics are moved to Delivered to client / QA.
    • Completed epics are moved to Done.
  • Every sprint, the epic planning manager should compare the Epics board for their cell with the corresponding sheet(s) of the epic planning spreadsheet and update the spreadsheet as necessary. This involves:
    • Adding new clients and/or epics.
    • Updating info about client and/or epic ownership.
    • Removing entries for clients and/or epics from future months based on contract and/or completion status.

Recording High-Level Information about Epics

We keep a record of all epics that we work on (except onboarding epics) in the Time / Estimates sheet of the epic planning spreadsheet so that high-level info (such as who estimated and led an epic, and how long it took to complete) can be referenced as necessary in the context of future discoveries.

As part of the epic planning process, the epic planning manager is responsible for keeping the Time / Estimates sheet up-to-date by:

  • Adding entries for new epics.
  • Updating entries for completed epics.

Tracking Cell Member Availability

To be able to determine capacity allocations for individual projects, we need to track cell member availability. As an epic planning manager you should:

  • Keep a look out for newcomers and core members joining or leaving the team, and add their details to the epic planning spreadsheet.
    • For newcomers this includes adding onboarding time to the onboarding section and specifying their availability in the availability section of the epic planning spreadsheet. Only make these updates when the corresponding information is fully public, i.e., the newcomer should know whether they have been accepted or not by the time these updates are made.
    • Availability for each member is calculated in full-time weeks. For example, if someone's commitment is:
      • 40h/week, their availability will be 40 / 40 = 1.
      • 30h/week, their availability will be 30 / 40 = 0.75.
    • If you prefer, you can also specify availability of individual cell members in hours per week. Just note that if you do, you'll also need to modify the calculation of total availability accordingly. (I.e., instead of just summing up the availability of the cell members to get the number of person-months available for each month, you'll need to sum up the weekly hours and divide the sum by 40.)
    • For team members leaving the team, make sure to remove (or reset to zero) their availability for the remaining months of the year.
  • Handle requests from cell members to change their weekly hour commitments, if the requested commitment is in the range of 30-40h per week:
    • Outside of that range, refer to the CEO: We generally avoid commitments that are lower or higher than 30-40h/week because they may
      • prevent cell members from taking some types of tasks,
      • increase overhead for commitments below 30h/week, and
      • can lead to burnout for commitments that exceed 40h/week.
    • However, temporary changes lasting 1-2 months that fall outside of the 30-40h/week range are generally acceptable.
    • If you need time to implement the change, for example to finish a round of recruitment, don't hesitate to discuss a specific date at which to make the change. Generally we agree to requests for changing weekly hour commitments, but not necessarily to implementing them immediately.
    • To implement the requested changes:
      • Update the cell member's availability in the epic planning spreadsheet to take the impact on your cell's total availability into account for epic planning.
      • Update the cell member's hours by via Tempo > Administration > Workload schemes:
        • Locate the team member's current workload scheme (e.g. 35h), and click Members.
        • Click Move to move the team member to the new workload scheme (e.g. 30h).
  • Check the calendar for vacations coming up in the next couple months:
    • If someone has scheduled time off for a total of 1 week or longer, comment on the cell(s) in the epic planning spreadsheet that represent their availability for the month(s) during which they will be away:
      • Mention the number of weeks they will be away.
      • Mention the remaining availability for the affected month(s).
    • Don't change their availability for the affected month(s) in the spreadsheet: Holidays are already taken into account in the holidays buffer, which reduces the cell's monthly availability according to the cap on the number of cell members that can be off at the same time. (That cap is usually 20%.)
  • Keep Role statistics for your cell up-to-date.
  • Keep the Discovery Duty rotations up-to-date in the Weekly Rotations Spreadsheet, taking into account latest role statistics.
    • This can happen at any time during the sprint, as long as the spreadsheet is checked at least once per sprint, and updated as necessary.
    • Discovery budget: 2.5% of the cell's total work hours (10h/week for 10 full times). The discovery budget and the discovery duty allocation are two different things. The weekly discovery duty allocation (5h/cell/week) is to be used for new tasks that pop up over the course of a sprint - it is funded by the discovery budget. Any leftover discovery budget can be used for discovery tasks that are planned in advance.
    • Members with a medium to high role load should be removed from DD rotations and re-added when their role load drops to a level that lets them take on new epics.

Capacity Requirements

  • For each client and epic, maintain a count of the amount of time required to complete the accepted project scope over the next months in the epic planning spreadsheet for your cell. This is used to inform recruitment needs (cf. below). Note that the amount of time required to complete the accepted scope of a project isn't always equal to the estimated budget for the project:
    • Work may progress more quickly than expected in some cases, allowing us to reduce capacity allocations for coming months.
    • In other cases there might be a need for additional work that was not accounted for in the original estimates, requiring us to increase capacity allocations for coming months.
  • Ensure delivery and bugfix deadlines for individual epics are on target. If that's not the case, comment on the epic(s) or directly on the epic planning spreadsheet, pinging epic owners as necessary and reminding them to:
    • Determine the impact of shifting deadlines and figure out how to minimize it.
    • Discuss the situation with the client (or the CEO in the case of accelerated epics), negotiate scope adjustments as needed, and make sure that the client (or CEO) is OK with them.
  • Coordinate with the team's recruitment manager to slow down/speed up recruitment as necessary.

Budgeting

Account types

Billable accounts are either fixed-price or work logged against them is billed hourly.

Fixed-price accounts

If an account is classified as fixed-price, this means that any hours logged in excess of the corresponding budget will not be billable to the client (and count as Overhead in the context of sustainability calculations).

Fixed-price accounts may belong to:

  • Fixed-price projects such as development of a specific set of features or the initial setup of a client instance.
    • Billing for these types of projects usually happens when they are complete. At that point we invoice the client for the full budget (i.e., the total number of hours quoted at the beginning of the project).
  • Epics with a fixed monthly budget such as <Client> instance maintenance.
    • Billing for these types of epics happens on an ongoing basis: We usually invoice the client for the recurring budget once per month.
Hourly billing

If an account is not classified as fixed-price, we usually bill the client once per month, for the number of hours logged against the account over the course of the previous month.

💡 Note that even if work is billed hourly, there might still be a (soft) monthly, yearly, or scope-based budget cap that we need to take into account for the purpose of both epic-level and cell-level planning (as well as sustainability management).

Reviewing account usage

Checking account associations

Getting accurate information about budget usage for individual projects requires that tickets be associated with correct accounts. Since tickets can't be created without setting an account, any questions that might come up around the correct account to use for a specific ticket are usually addressed at the time of ticket creation; and the choices being made as part of this process are usually correct. However, there are some edge cases where the chosen account for a ticket ultimately ends up being incorrect. For example:

  • A discovery ticket that starts out on the OpenCraft - Prospects account (a non-billable account) may need to be moved to the client account that corresponds to the project resulting from the discovery later on (after the prospect accepts the quote from the discovery). In practice, we sometimes end up forgetting about this step.
  • A firefighting issue may initially be associated with an internal account (e.g. OpenCraft - Instance Maintenance) when it should have been associated with a specific client's maintenance account.

Once per month we therefore need to check whether tickets worked on over the course of the previous month are using the right accounts, and make adjustments as necessary (cf. Sustainability Management).

This also helps us make sure that clients are billed correctly each month, and that the sustainability impact (or lack thereof) of individual tickets is correctly reflected in SprintCraft.

The process of checking ticket associations can be combined with the process of checking and recording actuals for the purpose of efficiency, and is described in the following section.

Checking and recording actuals

The main purpose of reviewing and recording actual time spent on individual accounts is to enable a high-level comparison between where we thought our time would go, and where it actually went over the course of a given month. This knowledge can help detect potential budget issues and allow us to follow up on them with epic owners. It can also inform decisions about capacity allocations for future months. (For example, you can set/adjust capacity allocations for ongoing internal work for coming months by calculating the average of actuals recorded for the last three months. You can also use actuals from past months to detect trends, which might be relevant for sustainability reviews.)

The combined process of checking account associations and checking and recording actuals looks like this:

  1. Go to the list of billable accounts and select the month for which to review account usage.
    • This list includes all billable accounts that the team logged time against over the course of the selected month. For the purposes of doing a cell-specific review, you can limit the steps listed below to accounts that either:
      • belong to a client that your cell owns, or:
      • are shared between multiple generalist cells (such as Self-hosted instances maintenance).
  2. For each relevant account:
    1. Click on the name of the account to see the list of tickets worked on and hours logged over the course of the selected month.
    2. [Checking account associations] Review the list of tickets that your cell worked on, looking for tickets that, from a high level, seem like they should be associated with a different account.
      • Follow up on any clear-cut cases right away. I.e., if it's clear that a specific ticket does not belong to the current account, and you don't have any doubts about which account the ticket should be associated with instead, go ahead and change the account on the ticket right away.
      • Make a note of any tickets that will require raising some follow-up questions to determine whether the current account is appropriate for them or not, and which accounts they should be moved to.
    3. [Checking and recording actuals] Add the total number of hours logged against the account by your cell to the Actual column for the selected month in the epic planning spreadsheet.
      • If the epic planning spreadsheet only has a single entry for a given client and the team logged time against multiple accounts belonging to that client over the course of the month you are reviewing, the actual to enter into the epic planning spreadsheet should be the sum of all hours logged against each individual account. For example, the epic planning spreadsheet may include a single entry listing capacity allocations for AwesomeClient™, while the work that we perform for that client is divided into maintenance and support-related tasks (meaning that for the month under review, you'll find hours logged against both AWESOMECLIENT-MAINTENANCE and AWESOMECLIENT-SUPPORT). To obtain the total number of hours to enter into the Actual column for AwesomeClient™, you can either sum up the actuals from AWESOMECLIENT-MAINTENANCE and AWESOMECLIENT-SUPPORT, or use the drop-down menu at the top of the page to search for and bring up the client's top-level Tempo entry which will list all tickets associated with any of the client's accounts, as well as the total number of hours logged across all accounts. (In the example above, the top-level Tempo entry would likely be called AwesomeClient.)
      • Actuals for small clients that don't have their own entry in the epic planning spreadsheet may be summed up under the actual for "Client Support" and/or "Client Maintenance".
      • If you found one or more tickets that might need to be moved to a different account, it may make sense to hold off on recording the number of hours logged against the current account at this stage, and complete this step once any remaining questions about account associations have been resolved (and tickets moved to different accounts as necessary). You should consider this approach if the number of hours logged against tickets to potentially move to a different account is substantial. If it's small (less than 10h), you can record the actual for the current account right away; there will be no need to update it again in the epic planning spreadsheet later (because doing so wouldn't impact any calculations that you might make based on actuals in a meaningful way).
  3. Go to the list of non-billable accounts and select the month for which to review account usage.
    • This list includes all non-billable non-cell accounts that the team logged time against over the course of the selected month. For the purposes of doing a cell-specific review, you only need to consider accounts that either:
      • belong to an accelerated epic that your cell has been working on, or:
      • belong to a company-wide role that is assigned to someone from your cell (such as Community Liaison), or:
      • are used to log other types of cell-level work that are tracked in the epic planning spreadsheet. (Aside from OpenCraft - Recruitment, which tracks all activities related to recruitment including onboarding time, accounts to check include, e.g., OpenCraft - Accounting, OpenCraft - Legal, and OpenCraft - Marketing. Hours for these accounts may be added to the actual recorded for the "Other OpenCraft" entry; cf. below).
  4. For each relevant account, click on the name of the account and repeat the steps for checking account associations and checking and recording actuals listed above.
  5. Go to the list of non-billable cell accounts and select the month for which to review account usage.
    • This list includes all non-billable cell responsibility accounts that the team logged time against over the course of the selected month.
  6. For each relevant account, click on the name of the account and repeat the steps for checking account associations and checking and recording actuals listed above.
    • The names of some accounts match corresponding entries in the epic planning spreadsheet more or less exactly. For example, to get the actual for the "Meetings" entry in the epic planning spreadsheet, you'll need to check the number of hours that your cell logged against the OpenCraft - Meetings account. However, there are are also some cases where there isn't a 1:1 match between account names and spreadsheet entries; we list them here for easy reference:
      • "Estimates/Prospects": OpenCraft - Prospects
      • "Management": OpenCraft - Cell management (and not OpenCraft - Management or OpenCraft - Stress management)
      • "Onboarding": OpenCraft - Recruitment
      • "Other OpenCraft":
        • OpenCraft - Accounting
        • OpenCraft - Client Management and Briefing
        • OpenCraft - Legal
        • OpenCraft - Marketing
        • OpenCraft - Sales Management
        • OpenCraft - Conferences
        • OpenCraft - Contributions
        • OpenCraft - Learning
      • "OpenCraft IM": OpenCraft - Instance Manager
      • "DevOps": OpenCraft - Instances DevOps
      • "<Open edX release> upgrades": OpenCraft - Instances upgrades
    • When it comes to checking account associations, pay special attention to the following cases:
      • OpenCraft - Instance Manager / OpenCraft - Instances DevOps: Look for tickets that could be moved to billable maintenance accounts.
      • OpenCraft - Instances Upgrades: Look for tickets that could be moved to billable maintenance or support accounts.
      • OpenCraft - Learning: Look for tickets from newcomer onboarding epics that could be moved to OpenCraft - Recruitment. (Tickets from these epics should be using the OpenCraft - Recruitment account by default, even if they are about learning some relevant technology or exploring part of our infrastructure.)
  7. [Checking account associations] Post the results of checking account associations as a comment on your cell's "Epic planning and sustainability management - <your cell>" epic. Include a summary of the changes that you made and list any open questions about further adjustments that you think should be made, pinging other people (epic owners, CEO/CTO, Administrative Specialist) as necessary.
  8. [Checking account associations] Adjust account associations as necessary based on the answers that you get.
  9. [Checking and recording actuals] As a last step, update the epic planning spreadsheet with any actuals that you held off on entering earlier.

Working with SprintCraft

Creating accounts
  • In Tempo, accounts are identified by a name (e.g. "Self-hosted instances maintenance") and a key (e.g. "SELFHOSTED-MAINTENANCE").
  • Account names may have a prefix such as "(Inc) - " which specifies the legal entity through which the corresponding work logs will be invoiced.
    • 💡 Note that SprintCraft does not display prefixes of account names on the Budget dashboard.
  • To tell SprintCraft about the existence of a specific Tempo account, create a corresponding SprintCraft account via Django Admin > Sustainability > Accounts:
    • The Name field of the SprintCraft account needs to match the name of the Tempo account exactly (including any prefixes).
      • 💡 This means that if an account is renamed in Tempo, the Name of the corresponding SprintCraft account will need to be updated accordingly.
    • If the account belongs to a fixed-price project, make sure to check Is fixed price.
      • 💡 As mentioned above, accounts for recurring maintenance (i.e., accounts with a fixed monthly budget) are considered fixed-price as well.
Division of responsibilities

The Administrative Specialist is responsible for creating Tempo accounts and corresponding SprintCraft accounts, as well as keeping account names in sync between Tempo and SprintCraft.

Creating budget entries
  • To tell SprintCraft about budgets for individual accounts, set them via Django Admin > Sustainability > Budgets:
    • The Date field of a budget entry should be set to the month to which the budget is supposed to apply.
    • The Hours field of a budget entry should be set to match the available budget.
    • The Account field of a budget entry must be set to the SprintCraft account to which the budget is supposed to apply.
      • As mentioned above, the Name field of the SprintCraft account needs to match the name of the corresponding Tempo account exactly. Otherwise SprintCraft will not be able to correctly associate budget entries with Tempo accounts.
  • If the budget for a specific account is the same for multiple months, there is no need to create a budget entry for each month: Just create a single entry for the first month to which the budget applies; SprintCraft will then automatically apply it to the following months.
    • 💡 This means you must explicitly reset the budget for a specific account to 0h when the corresponding contract ends (or when we've run out of budget for the account). Otherwise the budget will be applied to future months indefinitely.
  • If you create multiple budget entries for the same month (e.g. Jun 2021), SprintCraft will use the newest budget entry for display on the Budget dashboard and for sustainability calculations. (In other words, it is possible to overwrite earlier budget entries for a given month and account by creating new budget entries for the same month and account later on).
  • Budgets are specified in (full) hours per month. Decimals are not accepted.
Automation

For regular accounts (i.e., billable accounts that aren't bound to a fixed budget), budget entries are generated automatically once per month, based on the number of hours logged against these accounts in Tempo.

Division of responsibilities
  • The Administrative Specialist is responsible for setting initial budgets for fixed-price accounts (including maintenance).
  • Sustainability managers are responsible for retroactively adjusting monthly budgets for fixed-price accounts (excluding maintenance) to match actuals as necessary.
  • The Administrative Specialist is responsible for updating budgets for fixed-price accounts with recurring monthly budgets. This is necessary if the number of hours invoiced per month changes.
  • The Administrative Specialist is responsible for retroactively adjusting automatically-generated budgets for regular accounts. This is necessary if the number of hours invoiced for a specific month ends up differing from the number of hours logged over the course of that month.
Reviewing budget information
  • To review budget information for one or more accounts in SprintCraft:
    • Go to the Sustainability dashboard for your cell (e.g. Falcon).
    • Select the desired period to review (e.g. Jun 1st 2021–Dec 31st 2021).
    • Hover over the name of a specific account with your mouse to get a list of budgets entries for:
      • individual months of the current year, starting with the first budget entry that was explicitly set for that year in SprintCraft.
      • the first month following the selected period.
    • For high-level information about account budgets check the Period Goal / YTD Goal and Period Spent / YTD Spent columns. For each account:
      • The Period Goal column shows the total number of hours budgeted for the selected period (i.e., the sum of all budget entries for the selected period).
      • The YTD Goal column shows the total number of hours budgeted from the beginning of the first year within the selected period (i.e., Jan 1st in the example mentioned above) to the end of the next sprint.
      • The Period Spent column shows time logged during the selected period.
      • The YTD Spent column shows time logged from the beginning of the first year within the selected period.
    • At the bottom of the Budget dashboard you'll see an item called "Overhead". This item does not correspond to an account. Instead, it lists computed values for YTD Spent and Period Spent that represent the sum of non-billable hours logged against client accounts for the corresponding time spans (i.e., YTD and selected period).
  • If you find any inconsistencies or outdated information, adjust budgets in the Django admin as necessary (as described above).
  • Reload SprintCraft to see your changes reflected in popups and YTD Goal / Period Goal columns.

Choosing appropriate budgets

  • Getting accurate numbers for quarterly sustainability reviews requires creating appropriate budget entries for all client accounts belonging to your cell.
    • A client account belongs to your cell if the client owner is a member of your cell.
    • On the Budget dashboard, client accounts have a category of "Billable" and are listed at the top (above non-billable accounts).
  • Budget entries should reflect reality: For each month since the beginning of the (first) contract belonging to a given account, budget entries should match the number of billable hours that we had available for that month.
    • ⚡ If the sum of all budget entries for a given period exceeds the number of hours that we were able to bill for that period, this will artificially lower your cell's sustainability ratio and hide budget issues.
    • ⚡ If the sum of all budget entries for a given period is lower than the number of hours that we were able to bill for that period, this will artificially increase your cell's sustainability ratio and inflate budget issues (i.e., it will create the illusion of budget excess even if there wasn't any / even if it was lower that the sustainability numbers suggest).
    • When in doubt, check with the Administrative Specialist and see if budget entries need to be updated based on the number of hours that were billed to a client for a specific period.
Unused budgets from fixed-price projects

Note that the current implementation of SprintCraft does not take unused hours from fixed-price projects (which we sometimes refer to as "anti-overhead") into account for sustainability calculations. More specifically, when calculating Overhead, SprintCraft does not subtract the sum of unused billable hours from fixed-price projects (including maintenance) from the sum of non-billable hours that other client epics may have incurred.

Budgets 💰 vs. capacity allocations ⏱️

Keep in mind that budgets are not the same as capacity allocations: When a project first starts, we usually base capacity allocations for coming months on budgets. However, there are several situations where budgets and capacity allocations may no longer be tied together as closely as they were in the beginning of a project. For example:

  • We may have more budget left than hours needed to complete the scope of an epic in the coming months.
  • An epic may have a lot of budget left but the work may become completely blocked on the client, upstream etc. (which means we can lower capacity allocations for the coming months to 0h).
  • An epic may run out of budget before the agreed-upon scope has been completed.

Budgeting workflows for different types of epics

💡 Unless indicated otherwise, steps listed below are the responsibility of the epic planning and sustainability manager.

Fixed scope / Fixed budget

These types of epics typically represent fixed-price projects and are linked to fixed-price accounts.

  • Initially:
    • The Administrative Specialist sets the budget for the first month to the total number of hours that we have available for the project, and to 0h for the following month.
  • While project is running:
    • Adjust budget entries for past months as necessary: If actuals for past months differ significantly from budgets that were set initially, budget entries will need to be adjusted to match actuals more closely. (This makes it possible to get accurate numbers for quarterly sustainability reviews while the project is still running.)
    • Set budget for current month to remaining budget.
    • Reset budget to 0h from following month on.
    • If the project runs out of budget before its scope is complete:
      • Adjust budgets for past months to match actuals.
      • For the month during which the budget ran out, set the budget to the remaining hours for that month (i.e., the number of hours that was left in the budget at the end of the previous month).
      • Set the budget to 0h from the following month on.
  • When project is over:
    • If no budget is left, or the project went over budget (same as above):
      • Adjust budgets for past months to match actuals.
      • For the month during which the budget ran out, set the budget to the remaining hours for that month (i.e., the number of hours that was left in the budget at the end of the previous month).
      • Set the budget to 0h from the following month on.
    • If below budget: No changes needed (unless some budget updates were missed while the project was running, i.e., unless budgets and actuals still differ significantly for one or more past months).
    • Either way: Double-check that budget entries for individual months sum up to the total number of hours that the client paid for (i.e., the total number of hours from the initial quote/contract for the project, plus any budget extensions that the client approved in the meantime).
Dynamic scope / Monthly budget

These types of epics typically represent recurring maintenance work and are linked to fixed-price accounts.

  • Initially:
    • The Administrative Specialist sets the monthly budget to the number of billable hours that we have available per month.
    • If the end date of the current contract is known, the Administrative Specialist sets the budget for the month that follows the end date to 0h.
  • While project is running:
    • If the default number of hours invoiced per month changes, the Administrative Specialist will create a new budget entry for the month from which the change applies.
      • For example, if the monthly volume of work drops or increases significantly, the epic owner may work with the client to come up with a new monthly budget that better matches the recurring workload.
    • If an epic from this category happens to be billed hourly: At the beginning of each month, a new budget entry that matches time logged over the course of the previous month will be generated automatically.
  • When project is over:
    • Double-check that budgets for previous months match billed hours. (This should already be the case if budgets were updated while project was running.)
Dynamic scope / No specific budget

These types of epics typically represent recurring support work and are linked to regular (i.e., non fixed-price) accounts.

  • Initially:
    • If there is an approximate volume of hours that we are expected to work per month, you may optionally set the monthly budget to that volume. (The initial budget that you set will be overwritten by the next automated budget update So this is mainly helpful if you don't want SprintCraft to treat time logged over the course of the first month as overhead.)
  • While project is running:
    • At the beginning of each month, a new budget entry that matches time logged over the course of the previous month will be generated automatically.
    • If the number of hours invoiced for a specific month ends up differing from actuals, the Administrative Specialist will retroactively adjust budget entries as necessary.
  • When project is over:
    • Double-check that budgets for previous months match billed hours. (This should already be the case if budgets were updated while the project was running.)
Exceptions

Note that you may encounter some situations and/or edge cases that the instructions above don't explicitly cover. In these cases the main aspect to guide your decisions should be that budgets set in SprintCraft should never exceed the number of billable hours that we had available in the past, present, or future (as this would hide sustainability issues).

Sustainability Management

Each generalist and project cell is meant to be a sustainable entity by itself (with one exception -- the DevOps cell). Its members are the closest to most of the work that impacts its sustainability - the successful estimation and delivery of each client project.

Responsibility for tracking the volume of billable and non-billable hours (i.e., hours logged on internal/non-billable accounts) is decentralized to individual cells. See Cell Budgets for more details.

The sustainability manager of a cell is responsible for ensuring that the cell keeps the amount of non-billable hours logged in check. In particular, the sustainability manager must monitor the cell's sustainability ratio and make sure that the cell hits its current sustainability target (as listed under Cell-Specific Rules).

To help with this, the sustainability manager must perform the following activities:

Every sprint

  • Sustainability preview for upcoming sprint.
    • When planning the next sprint, the sustainability manager should:
      • Review the amount of billable and non-billable work scheduled by the cell for the next sprint.
      • Warn epic owners about any budget issues and get them to address those proactively. If the situation cannot be redeemed immediately, the sustainability manager should get a timeline and plan from the concerned epic owner(s) to resolve the issue.
    • The Budget section of the SprintCraft dashboard includes Left this sprint, Next sprint and Remaining for next sprint columns that can be used to estimate next sprint's sustainability.
    • The sustainability preview for a specific cell should be posted on the cell's epic planning and sustainability epic (or integrated into the cell's main epic planning update for the current sprint.)
    • See this section of the roles page for the template to use for the sustainability preview.

Every month

  • Accounts review for previous month.
    • At the beginning of each month, after the deadline for recording/adjusting time logs for the previous month, the sustainability manager should check that the tasks worked on over the course of the previous month are using the right accounts.
    • For the purpose of efficiency, this review can be combined with adding actuals for the previous month to the epic planning spreadsheet.
    • In particular, incidents that affected one or more client instances should use the clients' Instance Maintenance accounts instead of an internal DevOps account.
    • This review needs to happen before invoices are sent to clients, and results should be posted as a comment on the "Epic planning and sustainability management - <your cell>" epic.
    • See this section of the roles page for the template to use for the accounts review.

Every quarter

  • Sustainability review.
    • Every three months the sustainability manager should post an update on the forum about the current status of the cell's sustainability ratio and budgets for internal work, as well as plans for the coming months that ensure sustainable ratios.
    • This is done in January (Q1 update), April (Q2 update), July (Q3 update), and October (Q4 update).
    • It must wait until after client account budgets for the previous quarter are fully up-to-date in SprintCraft to make sure that the reported numbers are correct.
    • See this section of the roles page for a selection of templates you can use for the sustainability review.
  • Budget updates for non-billable cell accounts.
    • After each sustainability review, the sustainability manager should review and update budgets for non-billable cell accounts in SprintCraft, in coordination with owners of internal epics that are associated with these accounts.

Last update: 2022-11-23